Matterhorn Gotthard Bahn Updates- Mattertal Tunnel Project Between Tasch And Zermatt

The next generation project at MGBahn: The Mattertal Tunnel - the fast and safe connection between Täsch and Zermatt.

  • Planned start of construction: 2028
  • Planned completion: 2035
  • Cost estimate: approx. CHF 460 million (financed via the federal government’s STEP AS 2035)

Background:

  • The train route between Täsch and Zermatt is an important connection for the region.
  • Due to its exposed location in relation to weather events, the section is sensitive.
  • The route is regularly interrupted due to natural forces.
  • In order to create a safe and year-round public transport connection and to expand the service in line with timetables, a tunnel is planned.
  • The Mattertal Tunnel is part of the federal government's STEP Expansion Step 2035 project and is fully financed by the Federal Office of Transport.